158. Pile prep
- Short term 5B rev 5 April 2019 Ground Floor Production Lane
Sam Giddings (Hawkins)
2) Crop Cap | Basement: Grids 1-4/ A-C
Sam Giddings (Hawkins)   2
4) Install Pile Cap Cage | Basement: Grids 1-4/ A-C
Max Zuks (Hawkins)   1
6) Concrete Pour | Basement: Grids 1-4/ A-C
159. Membrane Ground Floor
May 06 2019 - May 14 2019 Short term 5B rev 5 April 2019 Ground Floor Production Lane
Sam Giddings (Hawkins)
1. Sikadur pile cap | Basement: Grids 1-4/ A-C
2. Install Corflex 60 and Site Weld | Basement: Grids 1-4/ A-C